NRC votes 4-1 to renew Entergy’s Pilgrim operating license 20 years

The Nuclear Regulatory Commission (NRC) has authorized Entergy’s (NYSE: ETR) 660-MW Pilgrim nuclear plant in Plymouth, Mass., to continue operating for an additional 20 years, until mid-2032.

Outgoing NRC Chairman Greg Jaczko was the lone vote against the license extension among the five-member commission. The controversial Jaczko, who announced his resignation May 21, was also the lone member of the panel to vote against issuance of new nuclear plant licenses in Georgia and South Carolina earlier this year – which were NRC’s first such approvals in more than 30 years.

The current 40-year operating license at Pilgrim was set to expire June 8. With the long-sought-after license extension now in hand, Entergy can perhaps focus more attention on negotiating a new labor agreement for the plant with Utility Workers Union of America Local 369.

The labor contract expired earlier this month, and Entergy hopes to reach a new four-year agreement. A federal mediator has been called in to help the parties overcome their differences.

Rep. Edward Markey, D-Mass., blasted the NRC’s decision to approve the license renewal while many opposition groups were still trying to raise concerns about the plant before NRC.

“The NRC shouldn’t be short circuiting the process and short-changing residents by moving forward with license approval before all the efforts to improve nuclear and environmental safety at Pilgrim Nuclear Power Station have been resolved,” Markey said in a May 25 news release.

Entergy Nuclear filed Pilgrim’s license renewal application on Jan. 25, 2006, making this the longest license review on record.

“During the NRC’s more than six years of review, people were afforded multiple chances to attend public meetings so regulators could get their input and hear their concerns,” said Entergy Nuclear CEO and Chief Nuclear Officer John Herron. “The public also had almost unlimited access to the NRC’s record of its extensive inspections of the plant.”

Entergy said the plant produces enough power to supply 10% of the electric demand in Massachusetts.

About Wayne Barber 4201 Articles
Wayne Barber, Chief Analyst for the GenerationHub, has been covering power generation, energy and natural resources issues at national publications for more than 20 years. Prior to joining PennWell he was editor of Generation Markets Week at SNL Financial for nine years. He has also worked as a business journalist at both McGraw-Hill and Financial Times Energy. Wayne also worked as a newspaper reporter for several years. During his career has visited nuclear reactors and coal mines as well as coal and natural gas power plants. Wayne can be reached at wayneb@pennwell.com.