FERC staff: Uplift payments trending up in ISOs/RTOs

08/21/2014

FERC staff evaluated uplift payments in energy and ancillary services markets, in an effort to begin a discussion with industry on market rules and operational practices.

Draft EIS: Badger-Coulee line to affect many resources, regardless of route alternatives chosen

Draft EIS: Badger Coulee line to affect many resources, regardless of route alternatives chosen

08/21/2014

The companies proposed two routes, a "northern" and a "southern" route, but those routes intersect one another at several locations and have three segments that are common to both routes, state agencies said.

Exelon, Pepco to Maryland PSC: Merger will leverage expertise in T&D

Exelon, Pepco to Maryland PSC: Merger will leverage expertise in T&D

08/21/2014 The companies said they are proposing several specific reliability guarantees for the Maryland customers of Pepco and Delmarva Power, adding that Exelon is committing that those goals will be subject to meaningful return on equity penalties for no...
Antelope Hills submits application for 345-kV line in North Dakota

Antelope Hills submits application for 345-kV line in North Dakota

08/21/2014

The line would convey power from the proposed Antelope Hills Wind Energy Project to the interconnection point at the existing switchyard of Basin Electric Power Cooperative's Antelope Valley station.

Virginia SCC: CPCN required for one of four proposed Potomac Edison projects

Virginia SCC: CPCN required for one of four proposed Potomac Edison projects

08/20/2014 The Millville project involves replacing the existing 556 aluminum conductor steel reinforced conductor with 556 aluminum conductor steel supported conductor on the 4.8-mile Virginia segment of the Millville (West Virginia)-Old Chapel (Virginia) 1...

Cal-ISO bid window for competitive projects closes; three submissions validated

08/20/2014

The ISO has so far validated three applications for two projects, and expects to announce validated applicants for the remaining three competitive projects in October.

Cal-ISO initiates competitive process for 500-kV Delaney-Colorado River line

08/20/2014

The ISO also posted key selection criteria for the project, which was included in the region’s 2013-2014 transmission plan.

Dominion Virginia Power proposes rebuild of 500-kV line in several Virginia counties

Dominion Virginia Power proposes rebuild of 500-kV line in several Virginia counties

08/20/2014

The project's in-service date is June 2018, and its estimated cost is about $106.1m, of which about $104.6m is for transmission line construction and about $1.5m is for station work.

FERC accepts Cal-ISO, project sponsor agreements for competitive projects

08/20/2014

The ISO submitted for FERC approval three APSAs related to the Gates–Gregg, Sycamore–Penasquitos and Imperial Valley Element competitive solicitation projects; FERC has so far accepted two.

Maryland PSC waives CPCN requirement for Pepco reconductoring project

Maryland PSC waives CPCN requirement for Pepco reconductoring project

08/19/2014

PJM Interconnection has directed Pepco to provide an interconnection between a planned new generation facility that will be located adjacent to existing Pepco right-of-way containing four existing 230-kV overhead transmission lines.